Hello Srinivasrao,
Planning calendar depend on the factory calendar. Whenever changes in factory calendar, planning calendar need to be updated.
- Again in planning calendar have some special future '
See below picture
Ex. Period fall on day which holiday in that case system provide the above option: consider the following day, Previous day, and in "No new Period day" system not create any period and "DO not Displace" ( consider a same day) in planning calendar period.
Select one of the option as per your requirement
- If you want to calculate the first three day as working day in planning calendar
Create the calculation rule like as below
Select the Rule : Weeks (week Days)
Enter : 1, 2,3 ( In this case system consider the every week Monday, Tuesday, Wednesday)
you can select any day with in week
But on particular day period fall on holiday system then system create new period with above logic
Please check and confirm the same
Thanks & Regards
Umesh Mali